• Zinc production factory

    90,000 m2 site with 20 main structures

    Location: Kunming, SE China

    3 weeks scanning, 2 weeks processing, 2 weeks modelling

    10 weeks drawing generation

     

    Deliverables:

    • Point cloud data
    • Detailed 2D site layout and plot plan
    • Accurate 2D equipment and piping layout drawings
    • Detailed 3D models of selected areas in the workshops
    • Updated process drawing (PFD & PID)

    Sub-millimetre inspection of marine propulsion components

    Various steel parts of up to 2.5 m in length

    Location: Jiangsu and Ningxia

     

    Deliverables:

    • Documentation of survey results (actual vs. nominal)
    • Overall object dimensions
    • Flatness measurements
    • Perpendicularities
    • Bolt hole locations
    • Radii verification
    • Cylinder roundness
    • Spatial centre line verification

    Specialty chemicals factory with limited technical documentation

    30,000 m2 site

    3 workshops, 5 buildings

    Location: Changchun, NE China

    4 days scanning

    5 days processing, 2 weeks modeling, 6 weeks drawing generation

     

    Deliverables:

    • Point cloud data
    • Detailed 2D site layout and plot plan
    • Accurate 2D equipment and piping layout drawings
    • Detailed 3D models of selected areas in the workshops
    • Updated process drawings

    Full as-built laser scan of a drilling rig

    Data capture for modelling purposes in Aveva PDMS software

    Location: Offshore, coast of Indonesia

    13 days of data capture (320 scan positions)

    25 days of data processing

     

    Deliverables:

    • Unified point cloud database
    • Registered colour scan data
    • Panoramic images 
    • Leica TruView files 
    • AutoDesk Navisworks files

    Pipe bridge

    Location: SCIP Shanghai, China

    3 hours scanning

    2 weeks modelling.

     

    Deliverables:

    • 3D model for pipes and steel structure 
    • Point cloud data 
    • Comparison of point-cloud data with engineering design
    • Updating of as-built drawings

    As-built documentation for facility relocation

    Location: Wuxi, Jiangsu Province

    Size: 7 levels of high density chemical structure

    1,200 labelled pipes

    7 days of scanning, 3 months modelling

     

    Deliverables:

    • Creation of a 3D model and combining as-built objects with existing isometric drawings
    • 3D point cloud data
    • 3D model
    • Tru View data
    • PDF drawings
    • Isometric drawings
    • Training

    As-built data capture of heritage building

    Scanning of façade of traditional courtyard house

    Location: Pudong, Shanghai

    2 hours scanning

    1 week data processing

     

    Deliverables:

    • 2D images
    • Point cloud data
    • Detailed 3D models of ornaments

    Steel structure verification scan

    As-built verification of entire structure for smooth placement of more than 1000 glass curtain wall pieces.

     

    Location: Shanghai, EXPO 2010 site

    1,000 m² of free form steel girders

    2 days scanning

    3 days processing and modeling

     

    Deliverables:

    • Point cloud data
    • As-built 3D modelling data